Onshore wind project J414, Freeborn County

Onshore wind project J414, Freeborn County is a 120 MW onshore wind request withdrawn in the MISO interconnection queue, in Freeborn County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2014 (completed)
  2. Withdrawn / abandonedOct 2018 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J414
Grid region
MISO (Midcontinent)
Connection point (POI)
Freeborn 161kV Substation on the Hayword - Freeborn - Winnebago 161kV line
Location
Freeborn County, Minnesota
Technology
Wind: 120 MW
Total requested
120 MW
Study phase
GIA
Queue status
Withdrawn
Entered queue
14 November 2014
Proposed online date
July 2019
Withdrawn
October 2018

Location

Marker shows the centre of Freeborn County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Freeborn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem