ONSHORE WIND · MISO

Onshore wind project G870, Freeborn County

Onshore wind project G870, Freeborn County is a 201 MW onshore wind request built and operating in the MISO interconnection queue, in Freeborn County, Minnesota.

Queue statusOperating
  1. PlanningQueued Oct 2007 (completed)
  2. ConsentedMay 2015 (completed)
  3. Construction (completed)
  4. OperatingDec 2009 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G870
Grid region
MISO (Midcontinent)
Connection point (POI)
Hayward - Winnebago 161 kV
Location
Freeborn County, Minnesota
Technology
Wind: 201 MW
Total requested
201 MW
Study phase
Network Upgrade
Queue status
Operational
Entered queue
2 October 2007
Agreement signed
11 May 2015
Proposed online date
December 2009
Came online
December 2009

Location

Marker shows the centre of Freeborn County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Freeborn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem