United States › Grid › Interconnection queues › Minnesota
ONSHORE WIND · MISOOnshore wind project G870, Freeborn County
Onshore wind project G870, Freeborn County is a 201 MW onshore wind request built and operating in the MISO interconnection queue, in Freeborn County, Minnesota.
Request details
- Queue ID
- G870
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Hayward - Winnebago 161 kV
- Location
- Freeborn County, Minnesota
- Technology
- Wind: 201 MW
- Total requested
- 201 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 2 October 2007
- Agreement signed
- 11 May 2015
- Proposed online date
- December 2009
- Came online
- December 2009
Location
Marker shows the centre of Freeborn County; the queue data does not give exact sites.
Other requests in Freeborn County
- Battery storage project J4089, Freeborn CountyBattery storage · 250 MW · in study
- Solar project J2845, Freeborn CountySolar · 200 MW · in study
- Onshore wind project E0036, Freeborn CountyOnshore wind · 162 MW · in study
- Battery storage project J2728, Freeborn CountyBattery storage · 150 MW · in study
- Onshore wind project J407, Freeborn CountyOnshore wind · 200 MW · built
- Onshore wind project J024, Freeborn CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project G871, Freeborn CountyOnshore wind · 201 MW · withdrawn
- Onshore wind project G671, Freeborn CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G855, Freeborn CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J3029, Freeborn CountyOnshore wind · 153 MW · withdrawn
- Solar project J1298, Freeborn CountySolar · 150 MW · withdrawn
- Solar project J1128, Freeborn CountySolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem