United States βΊ Grid βΊ Interconnection queues βΊ Minnesota
SOLAR Β· MISOSolar project J1298, Freeborn County
Solar project J1298, Freeborn County is a 150 MW solar request withdrawn in the MISO interconnection queue, in Freeborn County, Minnesota, connecting to SMMPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2019 (completed)
- Withdrawn / abandonedFeb 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J1298
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- SMMPA
- Connection point (POI)
- Hayward - Murphy Creek 161kV Line
- Location
- Freeborn County, Minnesota
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 29 April 2019
- Proposed online date
- December 2021
- Withdrawn
- February 2023
Location
Marker shows the centre of Freeborn County; the queue data does not give exact sites.
Power plants in Minnesota Β· Transmission lines in Minnesota
Other requests in Freeborn County
- Battery storage project J4089, Freeborn CountyBattery storage Β· 250 MW Β· in study
- Solar project J2845, Freeborn CountySolar Β· 200 MW Β· in study
- Onshore wind project E0036, Freeborn CountyOnshore wind Β· 162 MW Β· in study
- Battery storage project J2728, Freeborn CountyBattery storage Β· 150 MW Β· in study
- Onshore wind project G870, Freeborn CountyOnshore wind Β· 201 MW Β· built
- Onshore wind project J407, Freeborn CountyOnshore wind Β· 200 MW Β· built
- Onshore wind project J024, Freeborn CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project G871, Freeborn CountyOnshore wind Β· 201 MW Β· withdrawn
- Onshore wind project G671, Freeborn CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project G855, Freeborn CountyOnshore wind Β· 200 MW Β· withdrawn
- Onshore wind project J3029, Freeborn CountyOnshore wind Β· 153 MW Β· withdrawn
- Solar project J1128, Freeborn CountySolar Β· 150 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem