πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Minnesota

ONSHORE WIND Β· MISO

Onshore wind project J3029, Freeborn County

Onshore wind project J3029, Freeborn County is a 153 MW onshore wind request withdrawn in the MISO interconnection queue, in Freeborn County, Minnesota, connecting to ITC MIDWEST.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3029
Grid region
MISO (Midcontinent)
Utility / transmission owner
ITC MIDWEST
Connection point (POI)
Freeborn
Location
Freeborn County, Minnesota
Technology
Wind: 153 MW
Total requested
153 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
June 2026
Withdrawn
December 2025

Location

Marker shows the centre of Freeborn County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Freeborn County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem