ONSHORE WIND Β· MISO

Onshore wind project J024, Freeborn County

Onshore wind project J024, Freeborn County is a 201 MW onshore wind request withdrawn in the MISO interconnection queue, in Freeborn County, Minnesota.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2009 (completed)
  2. Withdrawn / abandonedJan 2010 (project stopped here)
  3. ConsentedJan 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J024
Grid region
MISO (Midcontinent)
Connection point (POI)
ITC Midwest Hayward substation
Location
Freeborn County, Minnesota
Technology
Wind: 201 MW
Total requested
201 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
5 February 2009
Agreement signed
27 January 2010
Proposed online date
January 2010
Withdrawn
January 2010

Location

Marker shows the centre of Freeborn County; the queue data does not give exact sites.

Power plants in Minnesota Β· Transmission lines in Minnesota

Other requests in Freeborn County