Withdrawn queue requests in SPP (Southwest Power Pool) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,846382.9 GW
Active in queue152.4 GW692 requests
Agreement signed37.6 GW212 requests
Withdrawn1,846382.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,846 requests · page 5 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GEN-2022-239, Hempstead County
Solar
350 MWWithdrawn / abandoned Hempstead, ARSPP Feb 2023target 2028
Gas project GEN-2003-012, Crawford County
Gas
350 MWWithdrawn / abandoned Crawford, KSSPP Jul 2003target 2010
Gas project GEN-2007-030N, Buffalo County
Gas
350 MWWithdrawn / abandoned Buffalo, NESPP Jul 2007
Solar project GEN-2022-063, Hutchinson County
Solar
350 MWWithdrawn / abandoned Hutchinson, TXSPP Jul 20222025
Solar project GEN-2022-219, Dawson County
Solar
350 MWWithdrawn / abandoned Dawson, MTSPP Mar 2023target 2026
Onshore wind project GEN-2017-160, Cimarron County
Onshore wind
350 MWWithdrawn / abandoned Cimarron, OKSPP Nov 2017target 2020
Solar project GEN-2022-246, Kidder County
Solar
342 MWWithdrawn / abandoned Kidder, NDSPP Mar 2023target 2028
Gas project GEN-2000-010, Pulaski County
Gas
340 MWWithdrawn / abandoned Pulaski, ARSPP
Onshore wind project GEN-2005-017, Sherman County
Onshore wind
340 MWWithdrawn / abandoned Sherman, TXSPP Sep 2005target 2007
Solar project GEN-2022-228, Logan County
Solar
335 MWWithdrawn / abandoned Logan, OKSPP Feb 2023target 2028
Onshore wind project GEN-2010-028, Blaine County
Onshore wind
335 MWWithdrawn / abandoned Blaine, OKSPP May 2010target 2013
Solar project GEN-2023-158, Bailey County
Solar
335 MWWithdrawn / abandoned Bailey, TXSPP Oct 2023target 2029
Gas project GEN-2008-125, Hale County
Gas
330 MWWithdrawn / abandoned Hale, TXSPP Nov 2008target 2012
Gas project GEN-2008-128, Hale County
Gas
330 MWWithdrawn / abandoned Hale, TXSPP Dec 2008target 2013
Battery storage project GEN-2022-051, Bossier Parish County
Battery storage
325 MWWithdrawn / abandoned Bossier Parish, LASPP Jun 20222025
Solar project GEN-2022-224, Muskogee County
Solar
325 MWWithdrawn / abandoned Muskogee, OKSPP Feb 2023target 2028
Onshore wind project GEN-2017-109, Dawson County
Onshore wind
321 MWWithdrawn / abandoned Dawson, MTSPP Aug 2017target 2020
Onshore wind project GEN-2016-116, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Nov 2016target 2019
Gas project GEN-2010-043, Woodward County
Gas
320 MWWithdrawn / abandoned Woodward, OKSPP Sep 2010target 2017
Onshore wind project GEN-2015-042, Dixon County
Onshore wind
320 MWWithdrawn / abandoned Dixon, NESPP Oct 2015target 2017
Gas project GEN-2007-018, Pettis County
Gas
315 MWWithdrawn / abandoned Pettis, MOSPP Apr 2007target 2010
Solar project GEN-2024-269, Otter Tail County
Solar
315 MWWithdrawn / abandoned Otter Tail, MNSPP Mar 2025target 2030
Gas project GEN-2012-016, Woodward County
Gas
312 MWWithdrawn / abandoned Woodward, OKSPP Aug 2012target 2017
Onshore wind project GEN-2016-049, Rush County
Onshore wind
310 MWWithdrawn / abandoned Rush, KSSPP Mar 2016target 2018
Solar project GEN-2017-205, Mcpherson County
Solar
310 MWWithdrawn / abandoned Mcpherson, KSSPP Nov 2017target 2020
Wind + storage project GEN-2023-231, Crawford County
Wind + storage
310 MWWithdrawn / abandoned Crawford, KSSPP Oct 2023target 2028
Solar project GEN-2017-212, Cedar County
Solar
310 MWWithdrawn / abandoned Cedar, NESPP Nov 2017target 2021
Onshore wind project GEN-2018-032, Mcpherson County
Onshore wind
310 MWWithdrawn / abandoned Mcpherson, KSSPP May 2018target 2029
Onshore wind project GEN-2016-114, Mcpherson County
Onshore wind
310 MWWithdrawn / abandoned Mcpherson, KSSPP Oct 20202020
Gas project GEN-2009-002, Lubbock County
Gas
306 MWWithdrawn / abandoned Lubbock, TXSPP Jan 2009target 2012
Solar project GEN-2022-126, Caddo County
Solar
305 MWWithdrawn / abandoned Caddo, OKSPP Feb 2023target 2028
Solar project GEN-2017-008, Nuckolls County
Solar
305 MWWithdrawn / abandoned Nuckolls, NESPP Apr 2017target 2019
Solar project GEN-2022-175, Clay County
Solar
305 MWWithdrawn / abandoned Clay, NESPP Feb 2023target 2026
Solar project GEN-2018-118, Lea County
Solar
305 MWWithdrawn / abandoned Lea, NMSPP Nov 2018target 2021
Onshore wind project GEN-2015-038, Canadian County
Onshore wind
304 MWWithdrawn / abandoned Canadian, OKSPP Sep 2015target 2017
Solar + storage project GEN-2020-036, Cass County
Solar + storage
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Gas project GEN-2020-040, Cass County
Gas
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Solar project GEN-2019-031, Lea County
Solar
303 MWWithdrawn / abandoned Lea, NMSPP Apr 2019target 2021
Onshore wind project GEN-2018-068, Madison County
Onshore wind
302 MWWithdrawn / abandoned Madison, NESPP Oct 2018target 2027
Solar project GEN-2017-224, Johnson County
Solar
302 MWWithdrawn / abandoned Johnson, KSSPP Nov 2017target 2020
Solar project GEN-2017-228, Johnson County
Solar
302 MWWithdrawn / abandoned Johnson, KSSPP Nov 2017target 2020
Onshore wind project GEN-2018-017, Keith County
Onshore wind
302 MWWithdrawn / abandoned Keith, NESPP Apr 2018target 2020
Onshore wind project GEN-2017-200, Beadle County
Onshore wind
302 MWWithdrawn / abandoned Beadle, SDSPP Nov 2017target 2026
Onshore wind project GEN-2024-108, Scott County
Onshore wind
302 MWWithdrawn / abandoned Scott, KSSPP Mar 2025target 2031
Onshore wind project GEN-2010-052, Haskell County
Onshore wind
301 MWWithdrawn / abandoned Haskell, KSSPP Sep 2010target 2013
Onshore wind project GEN-2011-028, Ellis County
Onshore wind
301 MWWithdrawn / abandoned Ellis, OKSPP Mar 2011target 2014
Onshore wind project GEN-2009-063, Dewey County
Onshore wind
301 MWWithdrawn / abandoned Dewey, OKSPP Dec 2009target 2011
Onshore wind project GEN-2011-015, Dewey County
Onshore wind
301 MWWithdrawn / abandoned Dewey, OKSPP Mar 2011target 2013
Solar project GEN-2017-190, Bailey County
Solar
300 MWWithdrawn / abandoned Bailey, TXSPP Nov 2017target 2020
Onshore wind project GEN-2016-001, Beaver County
Onshore wind
300 MWWithdrawn / abandoned Beaver, OKSPP Feb 2016target 2018
Page 5 of 37

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)