πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2017-190, Bailey County

Solar project GEN-2017-190, Bailey County is a 300 MW solar request withdrawn in the SPP interconnection queue, in Bailey County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-190
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Roosevelt-Tolk 230kV
Location
Bailey County, Texas
Technology
Solar: 300 MW
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2017
Proposed online date
December 2020
Withdrawn
March 2022

Location

Marker shows the centre of Bailey County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bailey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem