Solar project GEN-2016-089, Bailey County

Solar project GEN-2016-089, Bailey County is a 100 MW solar request withdrawn in the SPP interconnection queue, in Bailey County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2016 (completed)
  2. Withdrawn / abandonedMar 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2016-089
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tap 230kV Roosevelt-Tolk Line
Location
Bailey County, Texas
Technology
Solar: 100 MW
Total requested
100 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
28 September 2016
Proposed online date
November 2018
Withdrawn
March 2017

Location

Marker shows the centre of Bailey County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bailey County