United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2015-038, Canadian County

Onshore wind project GEN-2015-038, Canadian County is a 304 MW onshore wind request withdrawn in the SPP interconnection queue, in Canadian County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2015 (completed)
  2. Withdrawn / abandonedJan 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2015-038
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Cimarron 345kV Substation
Location
Canadian County, Oklahoma
Technology
Wind: 304 MW
Total requested
304 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 September 2015
Proposed online date
December 2017
Withdrawn
January 2017

Location

Marker shows the centre of Canadian County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Canadian County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem