United States β€Ί Grid β€Ί Interconnection queues β€Ί Kansas

SOLAR Β· SPP

Solar project GEN-2017-224, Johnson County

Solar project GEN-2017-224, Johnson County is a 302 MW solar request withdrawn in the SPP interconnection queue, in Johnson County, Kansas, connecting to KCPL.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2017 (completed)
  2. Withdrawn / abandonedSep 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-224
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
KCPL
Connection point (POI)
Craig 345kV Substation
Location
Johnson County, Kansas
Technology
Solar: 302 MW
Total requested
302 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 November 2017
Proposed online date
December 2020
Withdrawn
September 2022

Location

Marker shows the centre of Johnson County; the queue data does not give exact sites.

Power plants in Kansas Β· Transmission lines in Kansas

Other requests in Johnson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem