πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

ONSHORE WIND Β· SPP

Onshore wind project GEN-2017-109, Dawson County

Onshore wind project GEN-2017-109, Dawson County is a 321 MW onshore wind request withdrawn in the SPP interconnection queue, in Dawson County, Montana, connecting to WAPA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2017 (completed)
  2. Withdrawn / abandonedMar 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2017-109
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WAPA
Connection point (POI)
Dawson Co - Ft Peck 230 kV
Location
Dawson County, Montana
Technology
Wind: 321 MW
Total requested
321 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
30 August 2017
Proposed online date
December 2020
Withdrawn
March 2022

Location

Marker shows the centre of Dawson County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Dawson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem