United States β€Ί Grid β€Ί Interconnection queues β€Ί Montana

ONSHORE WIND Β· WEST

Onshore wind project GI-0915, Dawson County

Onshore wind project GI-0915, Dawson County is a 220 MW onshore wind request withdrawn in the West interconnection queue, in Dawson County, Montana, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2009 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-0915
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
Ft. Peck-Dawson County 230kV
Location
Dawson County, Montana
Technology
Wind: 220 MW
Total requested
220 MW
Service type
NRIS and ERIS
Study phase
IAP
Queue status
Withdrawn
Entered queue
21 May 2009
Proposed online date
December 2012

Location

Marker shows the centre of Dawson County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Dawson County