United States βΊ Grid βΊ Interconnection queues βΊ Montana
ONSHORE WIND Β· SPPOnshore wind project GEN-2024-223, Dawson County
Onshore wind project GEN-2024-223, Dawson County is a 241 MW onshore wind request withdrawn in the SPP interconnection queue, in Dawson County, Montana, connecting to WAPA.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2025 (completed)
- Withdrawn / abandonedDec 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2024-223
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- WAPA
- Connection point (POI)
- Dawson County-Miles City 2 230 kV line
- Location
- Dawson County, Montana
- Technology
- Wind: 241 MW
- Total requested
- 241 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 1 March 2025
- Proposed online date
- June 2030
- Withdrawn
- December 2025
Location
Marker shows the centre of Dawson County; the queue data does not give exact sites.
Other requests in Dawson County
- Gas project G256, Dawson CountyGas Β· 45.0 MW Β· built
- Other project G409, Dawson CountyOther Β· 2.0 MW Β· built
- Solar project GEN-2022-219, Dawson CountySolar Β· 350 MW Β· withdrawn
- Onshore wind project GEN-2017-109, Dawson CountyOnshore wind Β· 321 MW Β· withdrawn
- Onshore wind project GI-0915, Dawson CountyOnshore wind Β· 220 MW Β· withdrawn
- Onshore wind project GI-0807, Dawson CountyOnshore wind Β· 220 MW Β· withdrawn
- Onshore wind project GEN-2016-105, Dawson CountyOnshore wind Β· 120 MW Β· withdrawn
- Onshore wind project GI-0724, Dawson CountyOnshore wind Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem