United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2017-160, Cimarron County
Onshore wind project GEN-2017-160, Cimarron County is a 350 MW onshore wind request withdrawn in the SPP interconnection queue, in Cimarron County, Oklahoma, connecting to OGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2017 (completed)
- Withdrawn / abandonedApr 2020 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-160
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Mathewson 345kV
- Location
- Cimarron County, Oklahoma
- Technology
- Wind: 350 MW
- Total requested
- 350 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 November 2017
- Proposed online date
- December 2020
- Withdrawn
- April 2020
Location
Marker shows the centre of Cimarron County; the queue data does not give exact sites.
Other requests in Cimarron County
- Onshore wind project GEN-2016-045, Cimarron CountyOnshore wind Β· 499 MW Β· built
- Onshore wind project GEN-2016-057, Cimarron CountyOnshore wind Β· 499 MW Β· built
- Onshore wind project GEN-2007-056, Cimarron CountyOnshore wind Β· 600 MW Β· withdrawn
- Onshore wind project GEN-2017-159, Cimarron CountyOnshore wind Β· 350 MW Β· withdrawn
- Onshore wind project GEN-2016-038, Cimarron CountyOnshore wind Β· 300 MW Β· withdrawn
- Onshore wind project GEN-2017-161, Cimarron CountyOnshore wind Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem