United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
SOLAR Β· SPPSolar project GEN-2017-212, Cedar County
Solar project GEN-2017-212, Cedar County is a 310 MW solar request withdrawn in the SPP interconnection queue, in Cedar County, Nebraska.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2017 (completed)
- Withdrawn / abandonedFeb 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2017-212
- Grid region
- SPP (Southwest Power Pool)
- Connection point (POI)
- Mark T. Moore 345kV Substation
- Location
- Cedar County, Nebraska
- Technology
- Solar: 310 MW
- Total requested
- 310 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 November 2017
- Proposed online date
- December 2021
- Withdrawn
- February 2018
Location
Marker shows the centre of Cedar County; the queue data does not give exact sites.
Other requests in Cedar County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem