United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
ONSHORE WIND Β· SPPOnshore wind project GEN-2015-076, Cedar County
Onshore wind project GEN-2015-076, Cedar County is a 158 MW onshore wind request withdrawn in the SPP interconnection queue, in Cedar County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2015 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingDec 2020 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2015-076
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Belden 115kv Substation
- Location
- Cedar County, Nebraska
- Technology
- Wind: 158 MW
- Total requested
- 158 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 30 September 2015
- Proposed online date
- December 2020
- Came online
- December 2020
Location
Marker shows the centre of Cedar County; the queue data does not give exact sites.
Other requests in Cedar County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem