πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent) (2022 requests) β€” page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown43582.2 GW
Active in queue82.2 GW435 requests
Agreement signed881 MW6 requests
Withdrawn56794.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

435 requests Β· page 5 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J3167, Fulton County
Solar
180 MWIn study Fulton, ILMISO Sep 2022target 2026
Solar project J2578, Tuscola County
Solar
180 MWIn study Tuscola, MIMISO Sep 2022target 2026
Solar project J2847, Starke County
Solar
180 MWIn study Starke, INMISO Sep 2022target 2026
Onshore wind project J2247, Marshall County
Onshore wind
178 MWIn study Marshall, ILMISO Mar 2022target 2024
Onshore wind project J2571, Tunica County
Onshore wind
177 MWIn study Tunica, MSMISO Sep 2022target 2024
Solar project J3059, Midland County
Solar
175 MWIn study Midland, MIMISO Sep 2022target 2026
Solar project J2258, Adams County
Solar
175 MWIn study Adams, ILMISO Mar 2022target 2024
Solar project J2876, Arenac County
Solar
175 MWIn study Arenac, MIMISO Sep 2022target 2025
Onshore wind project J2437, Lee County
Onshore wind
175 MWIn study Lee, ARMISO Sep 2022target 2027
Solar project J2629, Newton County
Solar
175 MWIn study Newton, TXMISO Sep 2022target 2026
Onshore wind project J2988, Humboldt County
Onshore wind
175 MWIn study Humboldt, IAMISO Sep 2022target 2025
Solar project J2675, Gladwin County
Solar
170 MWIn study Gladwin, MIMISO Sep 2022target 2025
Solar project J2754, Polk County
Solar
170 MWIn study Polk, TXMISO Sep 2022target 2026
Battery storage project J2653, Polk County
Battery storage
170 MWIn study Polk, IAMISO Sep 2022target 2027
Solar + storage project J2786, Allegan County
Solar + storage
170 MWIn study Allegan, MIMISO Sep 2022target 2024
Battery storage project J2655, Polk County
Battery storage
170 MWIn study Polk, IAMISO Sep 2022target 2026
Solar project J3053, Madison County
Solar
169 MWIn study Madison, MSMISO Sep 2022target 2024
Solar project J2873, Simpson County
Solar
165 MWIn study Simpson, MSMISO Sep 2022target 2027
Onshore wind project J2576, Louisa County
Onshore wind
164 MWIn study Louisa, IAMISO Sep 2022target 2025
Solar project J2714, St. Landry Parish County
Solar
162 MWIn study St. Landry Parish, LAMISO Sep 2022target 2027
Gas project J3152, Green County
Gas
160 MWIn study Green, WIMISO Sep 2022target 2027
Solar + storage project J3118, Morehouse Parish County
Solar + storage
160 MWIn study Morehouse Parish, LAMISO Sep 2022target 2026
Solar project J2608, Stevens County
Solar
160 MWIn study Stevens, MNMISO Sep 2022target 2026
Solar + storage project J2397, Calhoun County
Solar + storage
160 MWIn study Calhoun, ARMISO Sep 2022target 2025
Battery storage project J2997, Livingston County
Battery storage
160 MWIn study Livingston, MIMISO Sep 2022target 2025
Solar project J2651, East Baton Rouge Parish County
Solar
160 MWIn study East Baton Rouge Parish, LAMISO Sep 2022target 2026
Gas project J2946, Dubuque County
Gas
160 MWIn study Dubuque, IAMISO Sep 2022target 2027
Gas project J3154, Franklin County
Gas
160 MWIn study Franklin, IAMISO Sep 2022target 2027
Gas project J3153, Clinton County
Gas
160 MWIn study Clinton, IAMISO Sep 2022target 2027
Solar project J3175, Tunica County
Solar
160 MWIn study Tunica, MSMISO Sep 2022target 2026
Solar project J2747, Greene County
Solar
160 MWIn study Greene, INMISO Sep 2022target 2026
Solar project J3064, Perry County
Solar
157 MWIn study Perry, ILMISO Sep 2022target 2026
Solar project J2561, Yellow Medicine County
Solar
153 MWIn study Yellow Medicine, MNMISO Sep 2022target 2030
Battery storage project J2378, Macomb County
Battery storage
152 MWIn study Macomb, MIMISO Sep 2022target 2026
Solar project J1751, Wood County
Solar
151 MWAgreement signed Wood, WIMISO Apr 2022target 2026
Onshore wind project J2502, Morton County
Onshore wind
150 MWIn study Morton, NDMISO Sep 2022target 2025
Onshore wind project J1967, Champaign County
Onshore wind
150 MWIn study Champaign, ILMISO Mar 2022target 2025
Solar project J2740, Sunflower County
Solar
150 MWIn study Sunflower, MSMISO Sep 2022target 2029
Solar project J2678, Delta County
Solar
150 MWIn study Delta, MIMISO Sep 2022target 2025
Solar + storage project J2389, Adams County
Solar + storage
150 MWIn study Adams, ILMISO Sep 2022target 2026
Battery storage project J2731, Olmsted County
Battery storage
150 MWIn study Olmsted, MNMISO Sep 2022target 2025
Solar + storage project J2869, Sunflower County
Solar + storage
150 MWIn study Sunflower, MSMISO Sep 2022target 2027
Solar project J3145, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027
Solar project J3144, Putnam County
Solar
150 MWIn study Putnam, INMISO Sep 2022target 2027
Onshore wind project J2686, Muscatine County
Onshore wind
150 MWIn study Muscatine, IAMISO Sep 2022target 2026
Solar project J2875, Presque Isle County
Solar
150 MWIn study Presque Isle, MIMISO Sep 2022target 2025
Battery storage project J2326, Outagamie County
Battery storage
150 MWIn study Outagamie, WIMISO Sep 2022target 2025
Solar + storage project J2880, Jefferson County
Solar + storage
150 MWIn study Jefferson, ARMISO Sep 2022target 2026
Solar project J2401, Johnson County
Solar
150 MWIn study Johnson, ILMISO Sep 2022target 2025
Solar project J1566, Martin County
Solar
150 MWIn study Martin, MNMISO Feb 2022target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)