United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J3175, Tunica County
Solar project J3175, Tunica County is a 160 MW solar request in interconnection study in the MISO interconnection queue, in Tunica County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3175
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY MISSISSIPPI, LLC.
- Connection point (POI)
- Robinsonville 230kV
- Location
- Tunica County, Mississippi
- Technology
- Solar: 160 MW
- Total requested
- 160 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 14 September 2022
- Proposed online date
- October 2026
Location
Marker shows the centre of Tunica County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Tunica County
- Onshore wind project J866, Tunica CountyOnshore wind · 200 MW · under construction
- Solar project J1440, Tunica CountySolar · 160 MW · under construction
- Onshore wind project J2571, Tunica CountyOnshore wind · 177 MW · in study
- Solar project J2174, Tunica CountySolar · 390 MW · withdrawn
- Solar project J3261, Tunica CountySolar · 200 MW · withdrawn
- Solar project J2939, Tunica CountySolar · 150 MW · withdrawn
- Solar project J2432, Tunica CountySolar · 150 MW · withdrawn
- Solar + storage project J2857, Tunica CountySolar + storage · 150 MW · withdrawn
- Battery storage project J2015, Tunica CountyBattery storage · 90.0 MW · withdrawn
- Battery storage project J3177, Tunica CountyBattery storage · 80.0 MW · withdrawn
- Solar project J1287, Tunica CountySolar · 50.0 MW · withdrawn
- Battery storage project J1439, Tunica CountyBattery storage · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem