United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in ERCOT (Texas) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,408328.0 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,408 requests · page 5 of 29
ProjectCapacityStatusLocationRegionQueuedOnline
Scott Crossing Solar SLF
Solar + storage · FRESH AIR ENERGY II, LLC
364 MWIn study Haskell, TXERCOT Mar 2023target 2027
Channing Wind
Onshore wind
361 MWPaused / redesign Oldham, TXERCOT Dec 2023target 2028
Wildflower Storage
Battery storage · Wildflower Storage LLC
359 MWIn study Navarro, TXERCOT Jun 2025target 2028
Tetris Solar
Solar · NextEra Energy Interconnection Holdings LLC
359 MWIn study Zapata, TXERCOT Jul 2023target 2029
Tetris Solar (Alternative POI)
Solar
359 MWPaused / redesign Zapata, TXERCOT Jul 2023target 2028
Twinwood Solar 1
Solar · Twinwood PV1, LLC
358 MWIn study Waller, TXERCOT Mar 2024target 2027
Green Ocelot Solar
Solar + storage · Ocelot Solar LLC
357 MWIn study Kenedy, TXERCOT Jan 2025target 2028
Funston Solar (AEP POI)
Solar
355 MWPaused / redesign Jones, TXERCOT Sep 2023target 2028
Max 4 Wind
Onshore wind · Lake Creek Wind, LLC
353 MWIn study Haskell, TXERCOT Jul 2025target 2028
Sombrero Solar
Solar · Aurora Solar LLC
352 MWIn study Schleicher, TXERCOT Mar 2022target 2028
Brookesmith Storage
Battery storage · Brookesmith Storage LLC
351 MWIn study Brown, TXERCOT Apr 2025target 2029
HyFuels Green Lake Solar
Solar · HyFuels Green Lake Solar LLC
347 MWIn study Victoria, TXERCOT Sep 2022target 2027
Rabbit Hollow Energy Storage
Battery storage · Rabbit Hollow Energy Storage, LLC
342 MWIn study Mitchell, TXERCOT Dec 2024target 2028
Titus Low Carbon Ventures Solar 1
Solar · Vaquero Solar, LLC
338 MWIn study San Patricio, TXERCOT Oct 2023target 2028
Cielo Vista Power Gas Plant
Gas · Cielo Vista Power, LLC
335 MWIn study Duval, TXERCOT Aug 2025target 2028
River Boat Power Gas Plant
Gas · Champion Creek Power, LLC
334 MWIn study Mitchell, TXERCOT Aug 2025target 2028
Mountaineer Solar
Solar · Mustang Mountaineer Solar LLC
332 MWIn study Brown, TXERCOT Apr 2019target 2028
Andromeda Storage II
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Aug 2024
Andromeda Storage IIB
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Jul 2024
Radian Storage II
Battery storage
320 MWPaused / redesign Brown, TXERCOT Jul 2024
Jade Thunder Storage
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Jul 2024
Jade Flash Storage
Battery storage
320 MWPaused / redesign Scurry, TXERCOT Jul 2024
Radian Storage IIB
Battery storage
320 MWPaused / redesign Brown, TXERCOT Jul 2024
White Bright BESS
Battery storage · VLN, LLC
314 MWIn study Grayson, TXERCOT Mar 2025target 2029
Diablo Campo Storage
Battery storage · Diablo Campo Energy Center, LLC
314 MWIn study Goliad, TXERCOT Feb 2024target 2029
Wild Paw Storage
Battery storage · Wild Paw Energy Center, LLC
313 MWIn study Henderson, TXERCOT May 2024target 2028
Barkley Creek Solar
Solar · 174 Power Global Properties, LLC
312 MWIn study Lampasas, TXERCOT Aug 2025target 2029
Canyon Wind Alternative
Onshore wind
312 MWPaused / redesign Scurry, TXERCOT
Bulldog Power II
Gas · Bulldog Power II LLC
311 MWIn study Brazoria, TXERCOT Dec 2025target 2030
Bulldog Power (TEF - Due Diligence)
Gas · Bulldog Power LLC
311 MWIn study Brazoria, TXERCOT Nov 2023target 2027
Cielo Vista Storage
Solar + storage · Cielo Vista Storage, LLC
311 MWIn study Duval, TXERCOT Apr 2025target 2028
Royal River BESS
Battery storage · Royal River LLC
311 MWIn study Brazoria, TXERCOT Mar 2022target 2027
Prairie Branch BESS
Solar + storage · Prairie Branch Energy, LLC
310 MWIn study Montague, TXERCOT Sep 2025target 2028
Oak Tree Energy Storage
Battery storage · Live Oak Energy Storage, LLC
310 MWIn study Lavaca, TXERCOT Dec 2023target 2029
Cuhullin Wind
Onshore wind
310 MWPaused / redesign Bee, TXERCOT
Slager Lake Wind
Onshore wind · NextEra Energy Resources Interconnection Holdings, LLC
310 MWIn study Reagan, TXERCOT Sep 2025target 2029
Sweetheart BESS
Solar + storage · Sweetheart Energy, LLC
310 MWIn study Young, TXERCOT Aug 2025target 2029
Sunrose Renewable Energy Solar SLF
Solar + storage · Sunrose Renewable Energy LLC
310 MWIn study Austin, TXERCOT Apr 2024target 2029
Red Hollow Renewable Energy Solar SLF
Solar + storage · Red Hollow Renewable Energy LLC
309 MWIn study Archer, TXERCOT Jul 2024target 2028
Buffalo Prairie Storage
Solar + storage · Buffalo Meadow Energy Center, LLC
308 MWIn study Robertson, TXERCOT Jan 2023target 2028
Clay County Yang Storage
Battery storage · DM-CCY, LLC
308 MWIn study Clay, TXERCOT Dec 2024target 2028
Mensa BESS
Battery storage · BRP Mensa BESS LLC
307 MWIn study Pecos, TXERCOT Jun 2020target 2027
18-Alpha BESS
Battery storage · SCOUT ENERGY MANAGEMENT, LLC
307 MWIn study Cooke, TXERCOT Apr 2025target 2028
Haute Stockage
Battery storage
307 MWPaused / redesign Shackelford, TXERCOT Oct 2023target 2027
Team Ranch Storage
Battery storage · BAF Storage, LLC
307 MWIn study Tarrant, TXERCOT Jun 2024target 2027
Beaujolais BESS
Battery storage
307 MWPaused / redesign Lamar, TXERCOT Dec 2023target 2026
Cattle Drive Solar
Solar · NextEra Energy Interconnection Holdings, LLC
307 MWIn study Crane, TXERCOT Jun 2024target 2029
Axtell BESS
Battery storage · Axtell BESS LLC
307 MWIn study Mclennan, TXERCOT Oct 2024target 2029
Cuchillas BESS
Solar + storage · Gransolar Texas Two
307 MWIn study Webb, TXERCOT Sep 2023target 2028
Copperleaf Energy Storage
Battery storage · Copperleaf Energy Storage, LLC
307 MWIn study Wichita, TXERCOT Nov 2024target 2029
Page 5 of 29

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)