BATTERY STORAGE · ERCOTWhite Bright BESS
White Bright BESS is a 314 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Grayson County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0605
- Grid region
- ERCOT (Texas)
- Developer
- VLN, LLC
- Connection point (POI)
- Tap 345kV 1729 Valley South – Anna Switch 2373
- Location
- Grayson County, Texas
- Technology
- Battery: 314 MW
- Total requested
- 314 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 21 March 2025
- Proposed online date
- April 2029
Location
Marker shows the centre of Grayson County; the queue data does not give exact sites.
Other requests in Grayson County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem