White Bright BESS

White Bright BESS is a 314 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Grayson County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0605
Grid region
ERCOT (Texas)
Developer
VLN, LLC
Connection point (POI)
Tap 345kV 1729 Valley South – Anna Switch 2373
Location
Grayson County, Texas
Technology
Battery: 314 MW
Total requested
314 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
21 March 2025
Proposed online date
April 2029

Location

Marker shows the centre of Grayson County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Grayson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem