🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

ONSHORE WIND · ERCOT

Canyon Wind Alternative

Canyon Wind Alternative is a 312 MW onshore wind request suspended in the ERCOT interconnection queue, in Scurry County, Texas.

Queue statusPaused / redesign
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
23INR0526
Grid region
ERCOT (Texas)
Location
Scurry County, Texas
Technology
Wind: 312 MW
Total requested
312 MW
Queue status
Suspended

Location

Marker shows the centre of Scurry County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Scurry County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem