🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Royal River BESS

Royal River BESS is a 311 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Brazoria County, Texas.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0282
Grid region
ERCOT (Texas)
Developer
Royal River LLC
Connection point (POI)
Tap 138kV 42110 Angleton - 43381 West Columbia
Location
Brazoria County, Texas
Technology
Battery: 311 MW
Total requested
311 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
30 March 2022
Proposed online date
January 2027

Location

Marker shows the centre of Brazoria County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Brazoria County