United States › Grid › Interconnection queues
OCTARY USA · INTERCONNECTION QUEUESBattery storage interconnection queue in the USA — page 40
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Marick Rose BESS Battery storage · Marick BESS |
50.2 MW | In study |
| Fort Chadbourne Cattle BESS Battery storage · Fort Chadbourne BESS |
50.2 MW | In study |
| Beeman BESS Battery storage · Beeman BESS LLC |
50.2 MW | In study |
| Battery storage project GEN-2024-243, Crawford County Battery storage |
50.1 MW | In study |
| Voyager Storage Battery storage · EDF Renewables Development, Inc. |
50.1 MW | In study |
| Battery storage project 22-07253, Weld County Battery storage |
50.0 MW | In study |
| Battery storage project 24-242, Polk County Battery storage |
50.0 MW | In study |
| Battery storage project GEN-2023-SR9, Crosby County Battery storage |
50.0 MW | Agreement signed |
| Battery storage project AJ1-001, Mecklenburg County Battery storage |
50.0 MW | In study |
| Battery storage project AG2-370, Allen County Battery storage · Tillman Storage LLC |
50.0 MW | In study |
| Zion Energy Center - BESS Battery storage |
50.0 MW | Agreement signed |
| Willow Springs Solar 3 Battery storage |
50.0 MW | Agreement signed |
| Battery storage project GEN-2018-031, Jackson County Battery storage |
50.0 MW | Agreement signed |
| Kifer BESS 1 Battery storage |
50.0 MW | In study |
| Battery storage project AI2-042, Louisa County Battery storage |
50.0 MW | In study |
| Battery storage project 956218, Nash County Battery storage · Duke Energy Progress LLC |
50.0 MW | In study |
| Sandlot IFB Battery storage · Sandlot Energy LLC |
50.0 MW | In study |
| Battery storage project GEN-2024-SR17, Kay County Battery storage |
50.0 MW | In study |
| Flatrock Creek Storage I Battery storage |
50.0 MW | Agreement signed |
| Battery storage project IA-PNM 2022-10, Sandoval County Battery storage |
50.0 MW | In study |
| Edgewater Storage Battery storage · Edgewater Battery Storage LLC |
50.0 MW | In study |
| Battery storage project AH2-420, Crawford County Battery storage |
50.0 MW | In study |
| Battery storage project AG2-061, Lasalle County Battery storage · Aurora Solar LLC |
50.0 MW | In study |
| Tavern Energy LLC Battery storage · Tavern Energy, LLC |
50.0 MW | In study |
| Battery storage project Company JV, Carson City County Battery storage |
50.0 MW | Agreement signed |
| Timber Road Storage III Battery storage |
50.0 MW | Agreement signed |
| Battery storage project AG2-551, Randolph County Battery storage · Riverstart Solar Park VI LLC |
50.0 MW | In study |
| Battery storage project J1477, Scott County Battery storage |
50.0 MW | Agreement signed |
| Battery storage project GEN-2023-SR19, Jefferson County Battery storage |
50.0 MW | In study |
| Battery storage project Q315, Coconino County Battery storage |
50.0 MW | Paused / redesign |
| South Orchard Battery storage · Garden Reserve Energy, LLC |
50.0 MW | Agreement signed |
| Battery storage project J1229, Muscatine County Battery storage |
50.0 MW | Agreement signed |
| Battery storage project J1272, Vanderburgh County Battery storage |
50.0 MW | Under construction |
| Surplus; J1587 Battery storage |
50.0 MW | In study |
| Top Crop Generating Facility Battery storage · Blackstone Wind Farm, LLC |
50.0 MW | In study |
| Battery storage project AI1-088, Prince George County Battery storage |
50.0 MW | In study |
| Battery storage project BHCT G50, Pueblo County Battery storage · Black Hills Colorado Electric, LLC |
50.0 MW | In study |
| Battery storage project Q289, Maricopa County Battery storage |
50.0 MW | In study |
| Twin Groves Storage II Battery storage |
50.0 MW | Agreement signed |
| Trade Post Energy Storage Battery storage |
50.0 MW | Agreement signed |
| Battery storage project AH1-269, Pulaski County Battery storage · Claytor Energy Storage, LLC |
50.0 MW | In study |
| Battery storage project J3140, Porter County Battery storage |
50.0 MW | In study |
| Battery storage project J2045, Newton County Battery storage |
50.0 MW | In study |
| Battery storage project AI1-086, Greensville County Battery storage |
50.0 MW | In study |
| Battery storage project S1126, Knox County Battery storage |
50.0 MW | In study |
| Zinnia Storage Battery storage |
50.0 MW | Agreement signed |
| Battery storage project Q229, Maricopa County Battery storage |
50.0 MW | In study |
| Battery storage project AG2-341, Mecklenburg County Battery storage · Mighty Blue LLC |
50.0 MW | In study |
| Battery storage project GEN-2024-305, Marion County Battery storage |
50.0 MW | In study |
| Hardin Energy Center – Storage I Battery storage |
50.0 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)724 · 133.4 GW
- West (non-ISO utilities)352 · 82.2 GW
- MISO (Midcontinent)305 · 55.0 GW
- CAISO (California)175 · 48.7 GW
- SPP (Southwest Power Pool)198 · 31.4 GW
- PJM (Mid-Atlantic, Midwest)248 · 29.6 GW
- Southeast (non-ISO utilities)109 · 19.4 GW
- NYISO (New York)84 · 11.1 GW
- ISO-NE (New England)31 · 6,907 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)