United States › Grid › Interconnection queues › Indiana

BATTERY STORAGE · MISO

Battery storage project J2045, Newton County

Battery storage project J2045, Newton County is a 50.0 MW battery storage request in interconnection study in the MISO interconnection queue, in Newton County, Indiana, connecting to NORTHERN INDIANA PUBLIC SERVICE COMPANY.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2045
Grid region
MISO (Midcontinent)
Utility / transmission owner
NORTHERN INDIANA PUBLIC SERVICE COMPANY
Connection point (POI)
Goodland 138 kV
Location
Newton County, Indiana
Technology
Battery: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
28 March 2022
Proposed online date
September 2024

Location

Marker shows the centre of Newton County; the queue data does not give exact sites.

Power plants in Indiana · Transmission lines in Indiana

Other requests in Newton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem