United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2020 requests) — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,752246.2 GW
Active in queue117.0 GW635 requests
Agreement signed57.7 GW326 requests
Withdrawn1,752246.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,752 requests · page 4 of 36
ProjectCapacityStatusLocationRegionQueuedOnline
Robin 2
Solar + storage
308 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Muir Storage
Battery storage
305 MWWithdrawn / abandoned Marin, CACAISO Apr 2020target 2025
Solar + storage project GEN-2020-036, Cass County
Solar + storage
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
Gas project GEN-2020-040, Cass County
Gas
303 MWWithdrawn / abandoned Cass, NESPP Apr 20202023
BRP Pobeda BESS
Battery storage · BRP Pobeda BESS LLC
301 MWWithdrawn / abandoned ERCOT Nov 2020target 2028
Onshore wind project 379, Rosebud County
Onshore wind
301 MWWithdrawn / abandoned Rosebud, MTWest Jun 2020target 2022
Solar project AG1-523, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Onshore wind project J1757, Coles County
Onshore wind
300 MWWithdrawn / abandoned Coles, ILMISO Jun 2020target 2023
Battery storage project AG1-199, Lucas County
Battery storage · Occasio Power Management LLC
300 MWWithdrawn / abandoned Lucas, OHPJM Sep 2020target 2023
Solar + storage project IC-845, Mobile County
Solar + storage
300 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2020
Onshore wind project J1666, Ingham County
Onshore wind
300 MWWithdrawn / abandoned Ingham, MIMISO Jun 2020target 2023
Battery storage project AF2-414, Hudson County
Battery storage
300 MWWithdrawn / abandoned Hudson, NJPJM Mar 2020target 2023
Solar + storage project 1199, Power County
Solar + storage
300 MWWithdrawn / abandoned Power, IDWest Mar 2020target 2023
Cuomo Hydro 1
Battery storage · Renewable Energy Aggregators, Inc.
300 MWWithdrawn / abandoned Westchester, NYNYISO Jun 2020
Blue River Storage
Battery storage · Hecate Energy Blue River LLC
300 MWWithdrawn / abandoned Shelby, INPJM Sep 2020target 2023
Solar project AG2-053, Fulton County
Solar · Orchid Acres Solar Project, LLC
300 MWWithdrawn / abandoned Fulton, OHPJM Dec 2020target 2024
Solar project Affected System to BPA G0630, Deer Lodge County
Solar
300 MWWithdrawn / abandoned Deer Lodge, MTWest Apr 2020
Egc BESS
Battery storage · Juno Power Management LLC
300 MWWithdrawn / abandoned Nassau, NYNYISO Aug 2020
Declaration Energy Center
Solar · Declaration Energy Center, LLC
300 MWWithdrawn / abandoned Seneca, NYNYISO Jul 2020
Speedway ESS 2
Battery storage
300 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2020target 2024
Solar project AG1-524, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Onshore wind project AG1-399, Mclean County
Onshore wind · Wapella Bluffs Wind Project, LLC
300 MWWithdrawn / abandoned Mclean, ILPJM Sep 2020target 2024
Battery storage project AF2-411, Clinton County
Battery storage
300 MWWithdrawn / abandoned Clinton, PAPJM Mar 2020target 2023
Solar project J1753, Green County
Solar
300 MWWithdrawn / abandoned Green, WIMISO Jun 2020target 2024
Solar + storage project IC-844, Mobile County
Solar + storage
300 MWWithdrawn / abandoned Mobile, ALSoutheast Jan 2020
Miranda ESS 2
Battery storage
300 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2020target 2024
Amethyst Solar
Solar + storage
300 MWWithdrawn / abandoned Riverside, CACAISO Apr 2020target 2023
Swan ESS
Battery storage
300 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2020target 2025
Tremont BESS
Battery storage · Juno Power Management LLC
300 MWWithdrawn / abandoned Bronx, NYNYISO Aug 2020
Onshore wind project J1676, Mclean County
Onshore wind
300 MWWithdrawn / abandoned Mclean, ILMISO Jun 2020target 2023
Solar + storage project 1220, Klamath County
Solar + storage
300 MWWithdrawn / abandoned Klamath, ORWest Apr 2020target 2023
GYPSY ESS 2
Battery storage
300 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2024
Solar + storage project Q15, Pinal County
Solar + storage
300 MWWithdrawn / abandoned Pinal, AZWest Sep 2020target 2023
HI300SB Project
Solar + storage
300 MWWithdrawn / abandoned Grant, NMWest Mar 2020target 2022
Onshore wind project J1702, Shelby County
Onshore wind
300 MWWithdrawn / abandoned Shelby, ILMISO Jun 2020target 2023
Solar + storage project GEN-2020-009, Cotton County
Solar + storage
300 MWWithdrawn / abandoned Cotton, OKSPP Apr 20202025
Solar + storage project 464, Mccracken County
Solar + storage
300 MWWithdrawn / abandoned Mccracken, KYSoutheast Dec 2020
Mifflin
Solar + storage · Renewable Energy Aggregators, Inc.
300 MWWithdrawn / abandoned Sullivan, NYNYISO Apr 2020
Solar project AG1-522, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Solar project AG1-408, Fulton County
Solar
300 MWWithdrawn / abandoned Fulton, OHPJM Sep 2020target 2024
Solar + storage project 456, Limestone County
Solar + storage
300 MWWithdrawn / abandoned Limestone, ALSoutheast Sep 2020
Solar project AG1-119, Dekalb County
Solar · Leeward Renewable Energy Development, LLC
300 MWWithdrawn / abandoned Dekalb, ILPJM Aug 2020target 2023
Solar project 1202, San Juan County
Solar
300 MWWithdrawn / abandoned San Juan, UTWest Mar 2020target 2022
Solar project AG1-525, Sullivan County
Solar · PJM Solar Devco I, LLC
300 MWWithdrawn / abandoned Sullivan, INPJM Sep 2020target 2023
Cuomo Hydro 2
Battery storage · Renewable Energy Aggregators, Inc.
300 MWWithdrawn / abandoned Westchester, NYNYISO Jun 2020
Solar + storage project 4, Grant County
Solar + storage
300 MWWithdrawn / abandoned Grant, WAWest Apr 2020
Buchanan Point BESS III
Battery storage · Juno Power Management LLC
300 MWWithdrawn / abandoned Westchester, NYNYISO Oct 2020
Buchanan Point BESS
Battery storage · Juno Power Management LLC
300 MWWithdrawn / abandoned Westchester, NYNYISO Aug 2020
Liberty II Storage
Battery storage · Liberty Madison Storage LLC
300 MWWithdrawn / abandoned Madison, INPJM Mar 2020target 2022
Chapel Energy Storage Facility
Battery storage
300 MWWithdrawn / abandoned Anne Arundel, MDPJM Aug 2020target 2029
Page 4 of 36

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)