SOLAR + STORAGE Β· NYISO

Mifflin

Mifflin is a 300 MW solar + storage request withdrawn in the NYISO interconnection queue, in Sullivan County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1004
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Renewable Energy Aggregators, Inc.
Connection point (POI)
Coopers Corner 345 kV
Location
Sullivan County, New York
Technology
Solar: 300 MW Β· Battery
Total requested
300 MW
Queue status
Withdrawn
Entered queue
13 April 2020

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in New York Β· Transmission lines in New York

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem