United States βΊ Grid βΊ Interconnection queues βΊ New York
SOLAR + STORAGE Β· NYISOMifflin
Mifflin is a 300 MW solar + storage request withdrawn in the NYISO interconnection queue, in Sullivan County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1004
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Renewable Energy Aggregators, Inc.
- Connection point (POI)
- Coopers Corner 345 kV
- Location
- Sullivan County, New York
- Technology
- Solar: 300 MW Β· Battery
- Total requested
- 300 MW
- Queue status
- Withdrawn
- Entered queue
- 13 April 2020
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Other requests in Sullivan County
- Town Line Solar CSR Phase ISolar + storage Β· 240 MW Β· in study
- Town Line Solar Phase IISolar + storage Β· 60.0 MW Β· in study
- Eagle Creek HydroHydro Β· 0.8 MW Β· built
- Eagle Creek HydroHydro Β· 0.8 MW Β· built
- Sullivan County Power ProjectGas Β· 1,080 MW Β· withdrawn
- Coopers Corner BESSBattery storage Β· 300 MW Β· withdrawn
- Coopers Corner BESSBattery storage Β· 300 MW Β· withdrawn
- Coopers Corner Storage Project 1Battery storage Β· 250 MW Β· withdrawn
- Coopers Corner Storage Project 2Battery storage Β· 250 MW Β· withdrawn
- Town Line Solar CSR Phase ISolar + storage Β· 240 MW Β· withdrawn
- Sullivan County Solar & BESSSolar + storage Β· 200 MW Β· withdrawn
- Chaumont SolarSolar Β· 160 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem