United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOCoopers Corner Storage Project 2
Coopers Corner Storage Project 2 is a 250 MW battery storage request withdrawn in the NYISO interconnection queue, in Sullivan County, New York, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2023 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1529
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Coopers Corner Storage Project 2 LLC
- Connection point (POI)
- Coopers Corners 345 kV Substation
- Location
- Sullivan County, New York
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Queue status
- Withdrawn
- Entered queue
- 2 March 2023
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Other requests in Sullivan County
- Town Line Solar CSR Phase ISolar + storage · 240 MW · in study
- Town Line Solar Phase IISolar + storage · 60.0 MW · in study
- Eagle Creek HydroHydro · 0.8 MW · built
- Eagle Creek HydroHydro · 0.8 MW · built
- Sullivan County Power ProjectGas · 1,080 MW · withdrawn
- MifflinSolar + storage · 300 MW · withdrawn
- Coopers Corner BESSBattery storage · 300 MW · withdrawn
- Coopers Corner BESSBattery storage · 300 MW · withdrawn
- Coopers Corner Storage Project 1Battery storage · 250 MW · withdrawn
- Town Line Solar CSR Phase ISolar + storage · 240 MW · withdrawn
- Sullivan County Solar & BESSSolar + storage · 200 MW · withdrawn
- Chaumont SolarSolar · 160 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem