BATTERY STORAGE · NYISO

Coopers Corner Storage Project 2

Coopers Corner Storage Project 2 is a 250 MW battery storage request withdrawn in the NYISO interconnection queue, in Sullivan County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1529
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Coopers Corner Storage Project 2 LLC
Connection point (POI)
Coopers Corners 345 kV Substation
Location
Sullivan County, New York
Technology
Battery: 250 MW
Total requested
250 MW
Queue status
Withdrawn
Entered queue
2 March 2023

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Sullivan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem