United States › Grid › Interconnection queues › New York

BATTERY STORAGE · NYISO

Coopers Corner BESS

Coopers Corner BESS is a 300 MW battery storage request withdrawn in the NYISO interconnection queue, in Sullivan County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2023 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1652
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
ACE DevCo NC, LLC
Connection point (POI)
Coopers Corner 345 kV Substation
Location
Sullivan County, New York
Technology
Battery: 300 MW
Total requested
300 MW
Queue status
Withdrawn
Entered queue
20 December 2023

Location

Marker shows the centre of Sullivan County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Sullivan County