HYDRO · NYISOEagle Creek Hydro
Eagle Creek Hydro is a 0.8 MW hydro request built and operating in the NYISO interconnection queue, in Sullivan County, New York, connecting to O&R.
Request details
- Queue ID
- 375
- Grid region
- NYISO (New York)
- Utility / transmission owner
- O&R
- Developer
- Eagle Creek Hydro, LLC
- Connection point (POI)
- Rio 69kV Switchyard
- Location
- Sullivan County, New York
- Technology
- Hydro: 0.8 MW
- Total requested
- 0.8 MW
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 6 March 2012
- Came online
- January 2014
Location
Marker shows the centre of Sullivan County; the queue data does not give exact sites.
Other requests in Sullivan County
- Town Line Solar CSR Phase ISolar + storage · 240 MW · in study
- Town Line Solar Phase IISolar + storage · 60.0 MW · in study
- Eagle Creek HydroHydro · 0.8 MW · built
- Sullivan County Power ProjectGas · 1,080 MW · withdrawn
- MifflinSolar + storage · 300 MW · withdrawn
- Coopers Corner BESSBattery storage · 300 MW · withdrawn
- Coopers Corner BESSBattery storage · 300 MW · withdrawn
- Coopers Corner Storage Project 1Battery storage · 250 MW · withdrawn
- Coopers Corner Storage Project 2Battery storage · 250 MW · withdrawn
- Town Line Solar CSR Phase ISolar + storage · 240 MW · withdrawn
- Sullivan County Solar & BESSSolar + storage · 200 MW · withdrawn
- Chaumont SolarSolar · 160 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem