BATTERY STORAGE · NYISO

Buchanan Point BESS III

Buchanan Point BESS III is a 300 MW battery storage request withdrawn in the NYISO interconnection queue, in Westchester County, New York, connecting to ConEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2020 (completed)
  2. Withdrawn / abandonedApr 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1107
Grid region
NYISO (New York)
Utility / transmission owner
ConEd
Developer
Juno Power Management LLC
Connection point (POI)
Buchanan 345kV
Location
Westchester County, New York
Technology
Battery: 300 MW
Total requested
300 MW
Queue status
Withdrawn
Entered queue
19 October 2020
Withdrawn
April 2022

Location

Marker shows the centre of Westchester County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Westchester County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem