BATTERY STORAGE Β· CAISO

Muir Storage

Muir Storage is a 305 MW battery storage request withdrawn in the CAISO interconnection queue, in Marin County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedJul 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1697
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Ignacio Substation 230kV
Location
Marin County, California
Technology
Battery: 305 MW
Total requested
305 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
15 April 2020
Proposed online date
October 2025
Withdrawn
July 2020

Location

Marker shows the centre of Marin County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Marin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem