United States › Grid › Interconnection queues › California
ONSHORE WIND · CAISOBodega Bay Project
Bodega Bay Project is a 175 MW onshore wind request withdrawn in the CAISO interconnection queue, in Marin County, California, connecting to PGAE.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2007 (completed)
- Withdrawn / abandonedMar 2008 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 227
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Fulton-Ignacio 230kV #2 line
- Location
- Marin County, California
- Technology
- Wind: 175 MW
- Total requested
- 175 MW
- Study phase
- System Impact Study
- Queue status
- Withdrawn
- Entered queue
- 14 June 2007
- Proposed online date
- December 2010
- Withdrawn
- March 2008
Location
Marker shows the centre of Marin County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Marin County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem