ONSHORE WIND · CAISO

Bodega Bay Project

Bodega Bay Project is a 175 MW onshore wind request withdrawn in the CAISO interconnection queue, in Marin County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2007 (completed)
  2. Withdrawn / abandonedMar 2008 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
227
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Fulton-Ignacio 230kV #2 line
Location
Marin County, California
Technology
Wind: 175 MW
Total requested
175 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
14 June 2007
Proposed online date
December 2010
Withdrawn
March 2008

Location

Marker shows the centre of Marin County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Marin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem