πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Idaho

SOLAR + STORAGE Β· WEST

Solar + storage project 1199, Power County

Solar + storage project 1199, Power County is a 300 MW solar + storage request withdrawn in the West interconnection queue, in Power County, Idaho, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1199
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Borah substation
Location
Power County, Idaho
Technology
Solar: 300 MW Β· Battery
Total requested
300 MW
Service type
NRIS and ERIS
Study phase
Request assumed to be submitted to 2021 cluster
Queue status
Withdrawn
Entered queue
21 March 2020
Proposed online date
November 2023

Location

Marker shows the centre of Power County; the queue data does not give exact sites.

Power plants in Idaho Β· Transmission lines in Idaho

Other requests in Power County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem