United States › Grid › Interconnection queues › New York

SOLAR · NYISO

Declaration Energy Center

Declaration Energy Center is a 300 MW solar request withdrawn in the NYISO interconnection queue, in Seneca County, New York, connecting to NYSEG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1048
Grid region
NYISO (New York)
Utility / transmission owner
NYSEG
Developer
Declaration Energy Center, LLC
Connection point (POI)
Border City 115 kV
Location
Seneca County, New York
Technology
Solar: 300 MW
Total requested
300 MW
Queue status
Withdrawn
Entered queue
14 July 2020

Location

Marker shows the centre of Seneca County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Seneca County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem