United States › Grid › Interconnection queues › New York
BATTERY STORAGE · NYISOTrelina Energy Storage
Trelina Energy Storage is a 120 MW battery storage request in interconnection study in the NYISO interconnection queue, in Seneca County, New York, connecting to NYSEG.
Queue statusIn planning
- PlanningQueued Sep 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2030 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-207
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- NextEra Energy Resources Interconnection Holdings, LLC
- Connection point (POI)
- Border City to Station 168 115 kV
- Location
- Seneca County, New York
- Technology
- Battery: 120 MW
- Total requested
- 120 MW
- Queue status
- Active
- Entered queue
- 19 September 2024
- Proposed online date
- December 2030
Location
Marker shows the centre of Seneca County; the queue data does not give exact sites.
Other requests in Seneca County
- North Seneca Solar Project, LLCSolar · 90.0 MW · in study
- Trelina Solar Energy CenterSolar · 79.8 MW · in study
- Seneca Energy ExpansionOther · 17.6 MW · built
- Declaration Energy CenterSolar + storage · 550 MW · withdrawn
- Declaration Energy CenterSolar · 300 MW · withdrawn
- Crystal Storage ProjectBattery storage · 175 MW · withdrawn
- Gravel Road SolarSolar · 128 MW · withdrawn
- Gravel Road SolarSolar · 128 MW · withdrawn
- Gravel Road SolarSolar · 126 MW · withdrawn
- North SenecaSolar · 90.0 MW · withdrawn
- Suffragette Solar Energy CenterSolar · 50.0 MW · withdrawn
- North Seneca StorageBattery storage · 19.9 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem