Withdrawn queue requests in CAISO (California) — page 37

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,186619.9 GW
Active in queue188.6 GW429 requests
Agreement signed96.2 GW235 requests
Withdrawn2,186619.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,186 requests · page 37 of 44
ProjectCapacityStatusLocationRegionQueuedOnline
Tumbleweed Solar Generating Station
Solar
33.0 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2008target 2009
Golden Oasis
Solar
33.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2013target 2021
Phoenix Solar Generating Station
Solar
33.0 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2008target 2009
Gaucho Storage
Battery storage
32.4 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2018target 2021
Amaretti Solar
Solar + storage
32.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Western Geopower Unit 1
Geothermal
32.0 MWWithdrawn / abandoned Sonoma, CACAISO Mar 2007target 2015
Coriander
Solar + storage
32.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Iceberg Energy Storage
Battery storage
31.8 MWWithdrawn / abandoned Monterey, CACAISO Apr 2020target 2022
West Ford Flat Energy Storage 2
Battery storage
31.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2028
LYNX Solar
Solar
30.9 MWWithdrawn / abandoned Santa Barbara, CACAISO May 2017target 2021
Hanson Energy Center
Battery storage
30.8 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2020target 2023
Tatton Storage 1
Battery storage
30.6 MWWithdrawn / abandoned Mendocino, CACAISO Apr 2019target 2021
Apricot Energy Storage
Battery storage
30.6 MWWithdrawn / abandoned Fresno, CACAISO Apr 2020target 2023
Loriner Storage
Battery storage
30.5 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2019target 2022
Crowswest
Solar + storage
30.2 MWWithdrawn / abandoned Stanislaus, CACAISO Apr 2020target 2023
Victor Grid Stabilization Project
Battery storage
30.0 MWWithdrawn / abandoned San Joaquin, CACAISO Apr 2014target 2016
Big Horn 30MW PV Project
Solar
30.0 MWWithdrawn / abandoned San Diego, CACAISO Mar 2011target 2014
Fox Solar
Solar
30.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2013target 2016
Painted Hills II
Onshore wind
30.0 MWWithdrawn / abandoned Riverside, CACAISO Feb 2007target 2008
Cuckoo Energy Storage
Battery storage
30.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2022
Miguel BESS (Fka Miguel)
Battery storage
30.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2019
PV-1
Solar
30.0 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2008target 2011
Colinas De Oro
Battery storage
30.0 MWWithdrawn / abandoned Alameda, CACAISO Apr 2014target 2021
Calrenew-1
Solar
30.0 MWWithdrawn / abandoned Fresno, CACAISO Aug 2007target 2009
Sungen 1
Solar
30.0 MWWithdrawn / abandoned Kern, CACAISO May 2008target 2011
Collinsville Wind
Onshore wind
30.0 MWWithdrawn / abandoned Solano, CACAISO Jun 2006target 2014
Frontier Solar II (Fka Scatec Westside Solar Ranch II)
Solar
30.0 MWWithdrawn / abandoned Stanislaus, CACAISO Mar 2011target 2013
Zamora Solar
Solar
30.0 MWWithdrawn / abandoned Yolo, CACAISO Mar 2011target 2013
Tesla Wind Bank
Battery storage
30.0 MWWithdrawn / abandoned Alameda, CACAISO Apr 2014target 2016
Madera Power
Other
29.0 MWWithdrawn / abandoned Madera, CACAISO Dec 2007target 2011
Medeiros Solar
Solar
28.4 MWWithdrawn / abandoned Merced, CACAISO May 2016target 2026
Egp Solar 1
Solar
28.0 MWWithdrawn / abandoned San Diego, CACAISO Mar 2011target 2013
Harbor Cogeneration
Gas
28.0 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2011target 2015
Diablo Canyon P.P. #1 Unit
Nuclear
28.0 MWWithdrawn / abandoned San Luis Obispo, CACAISO Feb 2006target 2005
Freeborn
Solar
27.3 MWWithdrawn / abandoned Kern, CACAISO Apr 2020target 2023
Contra Costa Carbon Plant Reconnect (CCCPR)
Other
27.2 MWWithdrawn / abandoned Contra Costa, CACAISO Sep 2006target 2008
Deadhorse Wells Geothermal Project
Geothermal
27.0 MWWithdrawn / abandoned Mineral, NVCAISO Mar 2011target 2013
GWF Hanford Combined Cycle Power Plant
Gas
27.0 MWWithdrawn / abandoned Kings, CACAISO Jan 2008target 2013
Bme Otay Mesa Biomass Facility
Other
27.0 MWWithdrawn / abandoned San Diego, CACAISO May 2006target 2017
Marine Depot
Battery storage
26.6 MWWithdrawn / abandoned San Diego, CACAISO Apr 2019target 2026
Otay Mesa Energy Center Expansion
Gas
26.4 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2022
Chula Vista BESS Expansion
Battery storage
26.0 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Stowe Energy Storage (Fka Poway)
Battery storage
25.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2019
Challenger
Solar
25.0 MWWithdrawn / abandoned Los Angeles, CACAISO Mar 2011target 2014
Palen DRY Lake PV
Solar
25.0 MWWithdrawn / abandoned Riverside, CACAISO Oct 2007target 2009
Woodland Battery Project
Battery storage
25.0 MWWithdrawn / abandoned Yolo, CACAISO Mar 2015target 2017
Utica 25MW PV Project
Solar
25.0 MWWithdrawn / abandoned Kings, CACAISO Mar 2011target 2014
Henrietta Energy Storage
Battery storage
25.0 MWWithdrawn / abandoned Kings, CACAISO Apr 2015target 2020
Maria Pico Energy Storage Center
Battery storage
25.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2015target 2018
Favorito
Solar
25.0 MWWithdrawn / abandoned Kern, CACAISO Mar 2011target 2014
Page 37 of 44

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)