United States › Grid › Interconnection queues › California

ONSHORE WIND · CAISO

Collinsville Wind

Collinsville Wind is a 30.0 MW onshore wind request withdrawn in the CAISO interconnection queue, in Solano County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2006 (completed)
  2. Withdrawn / abandonedOct 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
113
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Birds Landing Switching Station 230kV bus
Location
Solano County, California
Technology
Wind: 30.0 MW
Total requested
30.0 MW
Study phase
Executed
Queue status
Withdrawn
Entered queue
30 June 2006
Proposed online date
December 2014
Withdrawn
October 2014

Location

Marker shows the centre of Solano County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Solano County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem