Sungen 1

Sungen 1 is a 30.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2008 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
403
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Midway Substation 230 kV Bus
Location
Kern County, California
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 May 2008
Proposed online date
December 2011
Withdrawn
December 2010

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem