🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Henrietta Energy Storage

Henrietta Energy Storage is a 25.0 MW battery storage request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2015 (completed)
  2. Withdrawn / abandonedJan 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1126
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Henrietta Substation - 70kV
Location
Kings County, California
Technology
Battery: 25.0 MW
Total requested
25.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
30 April 2015
Proposed online date
May 2020
Withdrawn
January 2016

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem