🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

BATTERY STORAGE · CAISO

Colinas De Oro

Colinas De Oro is a 30.0 MW battery storage request withdrawn in the CAISO interconnection queue, in Alameda County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2014 (completed)
  2. Withdrawn / abandonedJan 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1011
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Tesla Substation 115kV
Location
Alameda County, California
Technology
Battery: 30.0 MW
Total requested
30.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
30 April 2014
Proposed online date
March 2021
Withdrawn
January 2021

Location

Marker shows the centre of Alameda County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Alameda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem