Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 33 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1331, St. Clair County
Solar
100 MWAgreement signed St. Clair, MIMISO Apr 2019target 2025
Solar project J1407, Porter County
Solar
100 MWAgreement signed Porter, INMISO Apr 2019target 2025
Solar project J1314, Polk County
Solar
100 MWUnder construction Polk, WIMISO Apr 2019target 2025
Solar project J4127, Barron County
Solar
100 MWIn study Barron, WIMISO Sep 2025target 2029
SS100S
Solar
100 MWAgreement signed El Paso, TXWest Sep 2022target 2025
Solar project AI2-328, Madison County
Solar
100 MWIn study Madison, OHPJM Mar 2023target 2026
Solar project 130, Georgetown County
Solar
100 MWUnder construction Georgetown, SCSoutheast Jul 2019target 2021
Solar project G0586, Klickitat County
Solar
100 MWIn study Klickitat, WAWest Apr 2018target 2022
Solar project J3899, Putnam County
Solar
100 MWIn study Putnam, ILMISO Dec 2024target 2027
Solar project BHCT G52, Pueblo County
Solar
100 MWIn study Pueblo, COWest Jun 2024target 2026
Solar project J1820, Lee County
Solar
100 MWIn study Lee, ARMISO Jun 2020target 2026
Solar project J2179, Montgomery County
Solar
100 MWIn study Montgomery, MOMISO Aug 2021target 2024
Flatrock Creek Solar I
Solar
100 MWAgreement signed Allen, INPJM Mar 2020target 2029
Solar project J1219, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Solar project J4124, Trinity County
Solar
100 MWIn study Trinity, TXMISO Aug 2025target 2029
Solar project J1777, Perry County
Solar
100 MWIn study Perry, ILMISO Jun 2020target 2026
Solar project AG2-550, Randolph County
Solar · Riverstart Solar Park VI LLC
100 MWIn study Randolph, INPJM Feb 2025target 2024
Solar project AH2-068, Wood County
Solar
100 MWIn study Wood, OHPJM Jan 2022target 2027
San Bernard Solar
Solar · Sunchase Power
100 MWPaused / redesign Wharton, TXERCOT Jan 2017target 2022
Solar project J1916, Branch County
Solar
100 MWIn study Branch, MIMISO Oct 2023target 2026
Solar project J1124, Olmsted County
Solar
100 MWUnder construction Olmsted, MNMISO Mar 2018target 2024
Solar project J3128, East Feliciana Parish County
Solar
100 MWIn study East Feliciana Parish, LAMISO Sep 2022target 2026
Solar project J1587, Muskegon County
Solar
100 MWAgreement signed Muskegon, MIMISO Jun 2020target 2025
Solar project G0706, Morrow County
Solar
100 MWIn study Morrow, ORWest Oct 2021target 2024
Rockdale Solar
Solar
100 MWAgreement signed Somerset, PAPJM Sep 2019target 2028
Solar project GI-93, Macon County
Solar
100 MWAgreement signed Macon, MOSoutheast Nov 2020target 2026
Clermont County Solar Project
Solar
100 MWPaused / redesign Clermont, OHPJM Mar 2019target 2025
Solar project J1472, Jackson County
Solar
100 MWAgreement signed Jackson, MIMISO Apr 2019target 2024
Solar project J2297, Sunflower County
Solar
100 MWIn study Sunflower, MSMISO Sep 2021target 2026
Solar project GI-2024-04, Pueblo County
Solar
100 MWIn study Pueblo, COWest Apr 2024target 2028
Solar project AH1-664, Fleming County
Solar · Hummingbird Energy LLC
100 MWIn study Fleming, KYPJM Feb 2025
Ne100S
Solar
100 MWAgreement signed El Paso, TXWest Mar 2024target 2027
Solar project J1391, Dubois County
Solar
100 MWAgreement signed Dubois, INMISO Apr 2019target 2025
Solar project J3165, Breckinridge County
Solar
100 MWIn study Breckinridge, KYMISO Sep 2022target 2025
Nottingham Solar
Solar
100 MWPaused / redesign Harrison, OHPJM Mar 20192023
Solar project J2495, Benton County
Solar
100 MWIn study Benton, MNMISO Sep 2022target 2026
Steward Creek Solar
Solar · Steward Creek Solar, LLC
100 MWIn study Lee, ILPJM Mar 2020target 2023
Southwest Michigan Energy Center
Solar
100 MWAgreement signed Van Buren, MIPJM Dec 2017target 2027
Solar project J3828, Lapeer County
Solar
100 MWIn study Lapeer, MIMISO Apr 2024target 2028
Solar project AH2-010, Logan County
Solar
100 MWIn study Logan, OHPJM Oct 2021target 2024
Solar project J4046, Attala County
Solar
100 MWIn study Attala, MSMISO Jul 2025target 2030
Solar project GEN-2020-078, Washington County
Solar
100 MWAgreement signed Washington, NESPP Apr 2020target 2022
Blue Rock Solar
Solar
100 MWAgreement signed Buckingham, VAPJM Mar 2019target 2026
Solar project J1932, Gladwin County
Solar
100 MWIn study Gladwin, MIMISO Aug 2021target 2024
Solar project J1748, Desoto County
Solar
100 MWAgreement signed Desoto, MSMISO Jul 2020target 2025
Solar project J1904, Acadia Parish County
Solar
100 MWIn study Acadia Parish, LAMISO Aug 2021target 2028
Solar project J3379, Johnson County
Solar
100 MWIn study Johnson, ILMISO Apr 2024target 2028
Solar project Q254, Pinal County
Solar
100 MWAgreement signed Pinal, AZWest Mar 2017target 2022
Solar project J604, Sunflower County
Solar
100 MWAgreement signed Sunflower, MSMISO May 20162022
Tillman Solar Park
Solar
100 MWAgreement signed Allen, INPJM Sep 2020target 2029
Page 33 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)