SOLAR · MISOSolar project J2179, Montgomery County
Solar project J2179, Montgomery County is a 100 MW solar request in interconnection study in the MISO interconnection queue, in Montgomery County, Missouri, connecting to AMEREN MISSOURI.
Queue statusIn planning
- PlanningQueued Aug 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2024 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2179
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- MONTGOMERY
- Location
- Montgomery County, Missouri
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 6 August 2021
- Proposed online date
- October 2024
Location
Marker shows the centre of Montgomery County; the queue data does not give exact sites.
Other requests in Montgomery County
- Solar project J1352, Montgomery CountySolar · 100 MW · agreement signed
- Solar project J2726, Montgomery CountySolar · 248 MW · withdrawn
- Solar project J2425, Montgomery CountySolar · 150 MW · withdrawn
- Battery storage project J2438, Montgomery CountyBattery storage · 150 MW · withdrawn
- Solar project J987, Montgomery CountySolar · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem