πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Missouri

SOLAR Β· MISO

Solar project J987, Montgomery County

Solar project J987, Montgomery County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Montgomery County, Missouri, connecting to Ameren Missouri.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2018 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. ConsentedOct 2021 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J987
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Montgomery 161kV Substation
Location
Montgomery County, Missouri
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Under Construction
Queue status
Withdrawn
Entered queue
12 March 2018
Agreement signed
12 October 2021
Proposed online date
October 2023
Withdrawn
October 2025

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Missouri Β· Transmission lines in Missouri

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem