🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Missouri

SOLAR · MISO

Solar project J1352, Montgomery County

Solar project J1352, Montgomery County is a 100 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Montgomery County, Missouri, connecting to Ameren Missouri.

Queue statusConsented
  1. PlanningQueued Apr 2019 (completed)
  2. ConsentedJul 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1352
Grid region
MISO (Midcontinent)
Utility / transmission owner
Ameren Missouri
Connection point (POI)
Spencer Creek - Montgomery 345kV Line
Location
Montgomery County, Missouri
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
29 April 2019
Agreement signed
6 July 2023
Proposed online date
December 2024

Location

Marker shows the centre of Montgomery County; the queue data does not give exact sites.

Power plants in Missouri · Transmission lines in Missouri

Other requests in Montgomery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem