OCTARY USA · INTERCONNECTION QUEUESOnshore wind interconnection queue in the USA — page 3
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project GI-TC-2024-16, Laramie County Onshore wind |
400 MW | Agreement signed |
| Onshore wind project PIS089, Lincoln County Onshore wind |
400 MW | In study |
| Onshore wind project IA-PNM-2025-19, Torrance County Onshore wind |
400 MW | In study |
| Onshore wind project G0956, Benewah County Onshore wind |
400 MW | In study |
| Onshore wind project 836, Carbon County Onshore wind · PacifiCorp |
400 MW | Agreement signed |
| Bug Tussle Wind Project Onshore wind · Bug Tussle Wind, LLC |
397 MW | Agreement signed |
| Onshore wind project GI-1404, Billings County Onshore wind |
383 MW | In study |
| North Country Wind Onshore wind · NY North Country, LLC |
380 MW | In study |
| North Country Wind II Onshore wind · NY North Country, LLC |
380 MW | In study |
| Moon Chapel Wind Onshore wind · Orsted Onshore Development North America, LLC |
379 MW | In study |
| Paint Rock Wind Onshore wind · Orsted Onshore Development North America, LLC |
379 MW | In study |
| Onshore wind project 07-023, Jefferson County Onshore wind |
375 MW | Paused / redesign |
| Onshore wind project 07-022, Jefferson County Onshore wind |
375 MW | Paused / redesign |
| Skyrider Wind Onshore wind · NextEra Energy Interconnection Holdings, LLC |
370 MW | In study |
| Viento Bravo Wind Onshore wind · Webb Wind, LLC |
367 MW | In study |
| Channing Wind Onshore wind |
361 MW | Paused / redesign |
| Onshore wind project GEN-2022-161, Butler County Onshore wind |
360 MW | In study |
| Onshore wind project E0015, Franklin County Onshore wind · Interstate Power and Light Company (IPL) |
360 MW | In study |
| Max 4 Wind Onshore wind · Lake Creek Wind, LLC |
353 MW | In study |
| Longview Wind Onshore wind · Longview Wind, LLC |
353 MW | Agreement signed |
| Onshore wind project GEN-2020-067, Terry County Onshore wind |
353 MW | In study |
| West Munday Wind Onshore wind · Lake Creek Wind, LLC |
352 MW | Agreement signed |
| Onshore wind project G0955, Lincoln County Onshore wind |
350 MW | In study |
| Onshore wind project GEN-2016-141, Texas County Onshore wind |
350 MW | Agreement signed |
| Onshore wind project J3623, Sunflower County Onshore wind |
350 MW | In study |
| Onshore wind project J3521, Shelby County Onshore wind |
350 MW | In study |
| Onshore wind project GI-TC-2024-25, Weld County Onshore wind |
350 MW | In study |
| Onshore wind project GEN-2016-142, Texas County Onshore wind |
350 MW | Agreement signed |
| Onshore wind project J4203, Huron County Onshore wind |
350 MW | In study |
| Onshore wind project G0954, Lincoln County Onshore wind |
350 MW | In study |
| Onshore wind project 21-08242, Laramie County Onshore wind |
350 MW | In study |
| Panther Grove Wind Onshore wind |
350 MW | Agreement signed |
| Onshore wind project J3597, Lonoke County Onshore wind |
348 MW | In study |
| Onshore wind project Q347, Navajo County Onshore wind |
345 MW | In study |
| Baird North Wind Onshore wind · BMP Wind, LLC |
340 MW | Agreement signed |
| Onshore wind project J3991, Mclean County Onshore wind |
340 MW | In study |
| Alle Catt II Wind Onshore wind · Alle-Catt Wind Energy LLC |
339 MW | In study |
| Onshore wind project 408, Wheatland County Onshore wind |
326 MW | In study |
| Onshore wind project C013, Meagher County Onshore wind |
326 MW | In study |
| Onshore wind project J3798, Winnebago County Onshore wind |
320 MW | In study |
| Onshore wind project J3982, Lonoke County Onshore wind |
320 MW | In study |
| Onshore wind project G0585, Klickitat County Onshore wind |
313 MW | In study |
| Canyon Wind Alternative Onshore wind |
312 MW | Paused / redesign |
| Cuhullin Wind Onshore wind |
310 MW | Paused / redesign |
| Slager Lake Wind Onshore wind · NextEra Energy Resources Interconnection Holdings, LLC |
310 MW | In study |
| Onshore wind project J4056, Marshall County Onshore wind |
310 MW | In study |
| Onshore wind project Q370, Coconino County Onshore wind |
310 MW | In study |
| Canyon Wind Onshore wind · Canyon Wind Energy, LLC |
309 MW | Agreement signed |
| Laurel Wind Energy Center Onshore wind · LAUREL ENERGY CENTER, LLC |
307 MW | Agreement signed |
| Estrella Dorada Wind Onshore wind · Estrella Dorada Wind Farm, LLC |
306 MW | In study |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)229 · 63.5 GW
- ERCOT (Texas)180 · 52.5 GW
- MISO (Midcontinent)208 · 42.7 GW
- SPP (Southwest Power Pool)121 · 26.7 GW
- PJM (Mid-Atlantic, Midwest)50 · 7,885 MW
- NYISO (New York)18 · 2,919 MW
- Southeast (non-ISO utilities)8 · 2,649 MW
- CAISO (California)10 · 1,252 MW
- ISO-NE (New England)2 · 22.9 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)