United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Onshore wind interconnection queue in the USA — page 3

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown826200.1 GW
Active in queue200.1 GW826 requests
Agreement signed49.9 GW242 requests
Withdrawn4,524860.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

826 requests · page 3 of 17
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project GI-TC-2024-16, Laramie County
Onshore wind
400 MWAgreement signed Laramie, WYWest May 2023target 2029
Onshore wind project PIS089, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest Oct 2024target 2028
Onshore wind project IA-PNM-2025-19, Torrance County
Onshore wind
400 MWIn study Torrance, NMWest Mar 2025target 2028
Onshore wind project G0956, Benewah County
Onshore wind
400 MWIn study Benewah, IDWest Oct 2023target 2026
Onshore wind project 836, Carbon County
Onshore wind · PacifiCorp
400 MWAgreement signed Carbon, WYWest Dec 2016target 2027
Bug Tussle Wind Project
Onshore wind · Bug Tussle Wind, LLC
397 MWAgreement signed Lamar, TXERCOT Jan 2022target 2027
Onshore wind project GI-1404, Billings County
Onshore wind
383 MWIn study Billings, NDWest May 2014
North Country Wind
Onshore wind · NY North Country, LLC
380 MWIn study Franklin, NYNYISO Sep 2024target 2029
North Country Wind II
Onshore wind · NY North Country, LLC
380 MWIn study Franklin, NYNYISO Sep 2024target 2029
Moon Chapel Wind
Onshore wind · Orsted Onshore Development North America, LLC
379 MWIn study Tom Green, TXERCOT Feb 2025target 2028
Paint Rock Wind
Onshore wind · Orsted Onshore Development North America, LLC
379 MWIn study Concho, TXERCOT Jan 2024target 2028
Onshore wind project 07-023, Jefferson County
Onshore wind
375 MWPaused / redesign Jefferson, ORWest Sep 2007target 2012
Onshore wind project 07-022, Jefferson County
Onshore wind
375 MWPaused / redesign Jefferson, ORWest Sep 2007target 2012
Skyrider Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
370 MWIn study Pecos, TXERCOT Nov 2024target 2028
Viento Bravo Wind
Onshore wind · Webb Wind, LLC
367 MWIn study Jim Hogg, TXERCOT Oct 2025target 2028
Channing Wind
Onshore wind
361 MWPaused / redesign Oldham, TXERCOT Dec 2023target 2028
Onshore wind project GEN-2022-161, Butler County
Onshore wind
360 MWIn study Butler, KSSPP Feb 2023target 2029
Onshore wind project E0015, Franklin County
Onshore wind · Interstate Power and Light Company (IPL)
360 MWIn study Franklin, IAMISO Aug 2025target 2028
Max 4 Wind
Onshore wind · Lake Creek Wind, LLC
353 MWIn study Haskell, TXERCOT Jul 2025target 2028
Longview Wind
Onshore wind · Longview Wind, LLC
353 MWAgreement signed Dawson, TXERCOT Sep 2025target 2028
Onshore wind project GEN-2020-067, Terry County
Onshore wind
353 MWIn study Terry, TXSPP Apr 2020target 2026
West Munday Wind
Onshore wind · Lake Creek Wind, LLC
352 MWAgreement signed Knox, TXERCOT Nov 2024target 2028
Onshore wind project G0955, Lincoln County
Onshore wind
350 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project GEN-2016-141, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project J3623, Sunflower County
Onshore wind
350 MWIn study Sunflower, MSMISO Apr 2024target 2028
Onshore wind project J3521, Shelby County
Onshore wind
350 MWIn study Shelby, ILMISO Apr 2024target 2028
Onshore wind project GI-TC-2024-25, Weld County
Onshore wind
350 MWIn study Weld, COWest May 2024target 2028
Onshore wind project GEN-2016-142, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Onshore wind project J4203, Huron County
Onshore wind
350 MWIn study Huron, MIMISO Jun 2025target 2028
Onshore wind project G0954, Lincoln County
Onshore wind
350 MWIn study Lincoln, WAWest Oct 2023target 2026
Onshore wind project 21-08242, Laramie County
Onshore wind
350 MWIn study Laramie, WYWest Aug 2021target 2025
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Onshore wind project J3597, Lonoke County
Onshore wind
348 MWIn study Lonoke, ARMISO Apr 2024target 2028
Onshore wind project Q347, Navajo County
Onshore wind
345 MWIn study Navajo, AZWest Sep 2020target 2024
Baird North Wind
Onshore wind · BMP Wind, LLC
340 MWAgreement signed Callahan, TXERCOT May 2018target 2026
Onshore wind project J3991, Mclean County
Onshore wind
340 MWIn study Mclean, ILMISO Apr 2025target 2029
Alle Catt II Wind
Onshore wind · Alle-Catt Wind Energy LLC
339 MWIn study Cattaraugus, NYNYISO Jan 2017target 2026
Onshore wind project 408, Wheatland County
Onshore wind
326 MWIn study Wheatland, MTWest Feb 2021target 2024
Onshore wind project C013, Meagher County
Onshore wind
326 MWIn study Meagher, MTWest Jan 2021target 2024
Onshore wind project J3798, Winnebago County
Onshore wind
320 MWIn study Winnebago, IAMISO Mar 2024target 2028
Onshore wind project J3982, Lonoke County
Onshore wind
320 MWIn study Lonoke, ARMISO Dec 2024target 2030
Onshore wind project G0585, Klickitat County
Onshore wind
313 MWIn study Klickitat, WAWest Mar 2018target 2021
Canyon Wind Alternative
Onshore wind
312 MWPaused / redesign Scurry, TXERCOT
Cuhullin Wind
Onshore wind
310 MWPaused / redesign Bee, TXERCOT
Slager Lake Wind
Onshore wind · NextEra Energy Resources Interconnection Holdings, LLC
310 MWIn study Reagan, TXERCOT Sep 2025target 2029
Onshore wind project J4056, Marshall County
Onshore wind
310 MWIn study Marshall, IAMISO Aug 2025target 2030
Onshore wind project Q370, Coconino County
Onshore wind
310 MWIn study Coconino, AZWest Mar 2021target 2024
Canyon Wind
Onshore wind · Canyon Wind Energy, LLC
309 MWAgreement signed Scurry, TXERCOT May 2016target 2025
Laurel Wind Energy Center
Onshore wind · LAUREL ENERGY CENTER, LLC
307 MWAgreement signed Pecos, TXERCOT Jun 2023target 2027
Estrella Dorada Wind
Onshore wind · Estrella Dorada Wind Farm, LLC
306 MWIn study Duval, TXERCOT Jul 2025target 2029
Page 3 of 17

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)