United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project J3798, Winnebago County
Onshore wind project J3798, Winnebago County is a 320 MW onshore wind request in interconnection study in the MISO interconnection queue, in Winnebago County, Iowa, connecting to ITC MIDWEST.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J3798
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ITC MIDWEST
- Connection point (POI)
- Bison - Colby 345kV
- Location
- Winnebago County, Iowa
- Technology
- Wind: 320 MW
- Total requested
- 320 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 1
- Queue status
- Active
- Entered queue
- 27 March 2024
- Proposed online date
- June 2028
Location
Marker shows the centre of Winnebago County; the queue data does not give exact sites.
Other requests in Winnebago County
- Onshore wind project J3849, Winnebago CountyOnshore wind · 200 MW · in study
- Onshore wind project J3157, Winnebago CountyOnshore wind · 200 MW · in study
- Onshore wind project J495, Winnebago CountyOnshore wind · 200 MW · built
- Onshore wind project G695, Winnebago CountyOnshore wind · 200 MW · withdrawn
- Other project G104, Winnebago CountyOther · 118 MW · withdrawn
- Other project G121, Winnebago CountyOther · 6.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem