United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project G695, Winnebago County
Onshore wind project G695, Winnebago County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Winnebago County, Iowa.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2006 (completed)
- Withdrawn / abandonedJul 2012 (project stopped here)
- ConsentedJul 2012 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- G695
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Winco - Winnebago 161 kV
- Location
- Winnebago County, Iowa
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Study phase
- SPA - SIS
- Queue status
- Withdrawn
- Entered queue
- 24 October 2006
- Agreement signed
- 30 July 2012
- Proposed online date
- December 2008
- Withdrawn
- July 2012
Location
Marker shows the centre of Winnebago County; the queue data does not give exact sites.
Other requests in Winnebago County
- Onshore wind project J3798, Winnebago CountyOnshore wind Β· 320 MW Β· in study
- Onshore wind project J3849, Winnebago CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project J3157, Winnebago CountyOnshore wind Β· 200 MW Β· in study
- Onshore wind project J495, Winnebago CountyOnshore wind Β· 200 MW Β· built
- Other project G104, Winnebago CountyOther Β· 118 MW Β· withdrawn
- Other project G121, Winnebago CountyOther Β· 6.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem