United States › Grid › Interconnection queues › Idaho
ONSHORE WIND · WESTOnshore wind project G0956, Benewah County
Onshore wind project G0956, Benewah County is a 400 MW onshore wind request in interconnection study in the West interconnection queue, in Benewah County, Idaho.
Queue statusIn planning
- PlanningQueued Oct 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- G0956
- Grid region
- West (non-ISO utilities)
- Connection point (POI)
- TBD
- Location
- Benewah County, Idaho
- Technology
- Wind: 400 MW
- Total requested
- 400 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 6 October 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Benewah County; the queue data does not give exact sites.
Other requests in Benewah County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem