Solar + storage project 100, Benewah County

Solar + storage project 100, Benewah County is a 100 MW solar + storage request in interconnection study in the West interconnection queue, in Benewah County, Idaho, connecting to Avista Utilities.

Queue statusIn planning
  1. PlanningQueued Sep 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
100
Grid region
West (non-ISO utilities)
Utility / transmission owner
Avista Utilities
Connection point (POI)
Benewah 230 kV Station
Location
Benewah County, Idaho
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
NRIS and ERIS
Queue status
Active
Entered queue
27 September 2019
Proposed online date
December 2021

Location

Marker shows the centre of Benewah County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Benewah County