United States › Grid › Interconnection queues › Oregon

ONSHORE WIND · WEST

Onshore wind project 07-023, Jefferson County

Onshore wind project 07-023, Jefferson County is a 375 MW onshore wind request suspended in the West interconnection queue, in Jefferson County, Oregon, connecting to Portland General Electric.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2007 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2012 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
07-023
Grid region
West (non-ISO utilities)
Utility / transmission owner
Portland General Electric
Connection point (POI)
A new location between Boardman and Warm Springs
Location
Jefferson County, Oregon
Technology
Wind: 375 MW
Total requested
375 MW
Service type
Network resource (NRIS)
Queue status
Suspended
Entered queue
4 September 2007
Proposed online date
December 2012

Location

Marker shows the centre of Jefferson County; the queue data does not give exact sites.

Power plants in Oregon · Transmission lines in Oregon

Other requests in Jefferson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem